    Shenwan Power Plant 2 × 660MW Unit Raw Water Treatment Project 

    发布时间:2019-03-11

                               

    Shenwan Power Plant 2 × 660MW Unit Raw Water Pretreatment Project

    Raw water: river water;

    Water treatment capacity: 2400 m3/h

    Raw water turbidity: 60-170NTU

    Effluent turbidity: below 3NTU

    technological process:

    Raw water - high-density micro vortex mixer - high-density micro vortex flocculation sedimentation tank - effluent

    Project introduction:

    The power generation company is a central enterprise located in Longqiao Town, Lujiang River. The project will build two 660000 generator sets, with a total investment of 5 billion yuan.

    The raw water pretreatment station of the power plant adopts our company's proprietary technology "high-density micro vortex flocculation sedimentation and clarification water treatment technology", and the effluent after sedimentation is 3NTU, with stable operation, reliable effluent and good water quality.